| Introduction to Earned value Management |
|
|
| Thursday, 26 November 2009 13:52 |
|
Earned Value Analysis in the last years proved itself as one of the best system for project control. It's importance comes from thefact that we get an integrated vision checking both costs and schedule. In this article, I will try to introduce the EV concepts. This introduction should help you to apply straight the EV to your project. Before start with the definition, pleast consider that EV in its correct form would require all the quantities being expressed in term of money. Quite often this is not possible (expecially in large organizations) because such values are not shared with team leaders or because it is difficult to get them. In order to apply the EV concept we just need to substitute the "money" with "person day". Even if in this way we loose a bit of information related to project indirect costs, the results in term of control are still relevant. The most important variables in EV analysis are:
it represents the initial estimation for one activity. It's the cost of the activity if it is done as planned. If there are no planned cost, then we used planned days.
Earned value measures the project progress at a given date. It is the planned cost of the activities that were effectively closed. For example if at one give day I closed activities that were estimated (both direct and not direct costs) 5000 euros, then my EV will be 5000 euros. As for PV, it is possible to express EV in terms of person days of closed activities.
This value gives the real cost that we had (direct + not direct + other) to complete the activities at a given date.Even here we will be able to use the persons day, if cost are not available. In order to make the analysis we need to obtain the value of three basic variables at a specific date or at specific time interval (for example weekly) during the project.
In easy word, a negative CV means that we are spending more than planned (or using more person days), while a negative SV means that we are going late.
It is possible, in order to check the status of the project to create graphs with SPI and CPI and monitoring their values against the ideal value of one. Now it will be easier to understand the approach to follow in order to apply the concepts:
Following some examples about the project evaluation, starting from the graphical representation:
It is possible to extend EV concepts and to perform a better control on the project, using more complex tools and enriching them by using Management by Exceptions (MBE) concepts, but this will be handled in a different article. ( 0 Votes ) |






